The groundworks for the scaffolding to Taylor House and Stanley House will commence on Wednesday 7-10-26. This work comprises of digging scrapes 100mm deep x 2400mm long into the grassed areas around the three elevations of each building as part of the scaffold supports. The formed scrapes will have treated…
-

ALL RESIDENTS
The site accommodation units are being delivered on the morning of Tuesday 6-10-26, these are high sided containers that will be craned into position. Will all residents please ensure that roads on the two access routes marked below are kept clear of any parked vehicles. a. Scholars Walk to Pepys…
-
PAXMAN HOUSE
NOT STARTED Works have not yet commenced. LIKELY IMPACT: None NEXT Refer to the Construction Programme for planned timing.
-
MERIVALE HOUSE
NOT STARTED Works have not yet commenced. LIKELY IMPACT: None NEXT Refer to the Construction Programme for planned timing.
-
WORDSWORTH HOUSE
NOT STARTED Works have not yet commenced. LIKELY IMPACT: None NEXT Refer to the Construction Programme for planned timing.
-
STANLEY HOUSE
PREPARATION Pre-start preparations and resident access arrangements. LIKELY IMPACT: Low NEXT Scaffold installation.
-
TAYLOR HOUSE
SCAFFOLDING Scaffold erection progressing around the building. LIKELY IMPACT: Moderate / noisier NEXT Existing façade removal begins in completed scaffold areas.