What to Expect During the Works

A simple guide to the external wall remediation sequence at The Vie

The works will move around each building in planned stages. Not every stage will be taking place outside your apartment at the same time.

The construction sequence
1Scaffolding installed
Scaffolding is erected around the building to provide safe access for the external works. Once it reaches your level, balconies and terraces within the construction zone will be temporarily out of use.
Typical noise
More noticeable
2Existing cladding removed
The existing combustible external cladding and associated materials are carefully removed to expose the existing construction and allow concealed areas to be inspected.
Typical noise
Noisier
3A1 CP Board installed
The new non-combustible CP Board is installed as the works progress, providing a protective weathering layer ahead of the remaining facade build-up.
Typical noise
Relatively quiet
4Membranes & cavity barriers
New membranes, seals and cavity barriers are installed in accordance with the approved design. Critical details are inspected before they are covered by subsequent layers.
Typical noise
Relatively quiet
5Supporting rails installed
The supporting substructure for the new cladding is installed. This stage involves drilling and fixing into the primary structure and may be more noticeable inside apartments close to the working area.
Typical noise
More noticeable
6New A1 facade installed
The new dark brown Benx Supertech facade panels, flashings and associated external finishes are installed to complete the new external wall system.
Typical noise
Moderate
7Final inspections & making good
The completed areas are inspected, external building items removed for the works are reinstated where required, and any necessary making good is completed.
Typical noise
Generally quieter
8Scaffolding removed
Once the required works and inspections are complete and it is safe to do so, the scaffolding is dismantled and normal use of the affected external areas can resume.
Typical noise
More noticeable
A few things to remember
  • Noise will vary as the works move around the building. Higher-noise activities will be intermittent rather than continuous.
  • The sequence can overlap between different elevations, so the exact activity outside your apartment may differ from another part of the building.
  • Construction programmes can change due to site conditions, weather, access, materials, inspections and other dependencies.
  • Please check the Residents’ Portal regularly for the Construction Programme and News & Updates showing where works are taking place.

Important: This guide explains the typical sequence of works. Please refer to the Residents’ Portal for the latest programme and current activity affecting your building.